The shareholders of Romania's state nuclear company Nuclearelectrica approved the final investment decision for the Doicești small modular reactor (SMR) project on 12 February 2026, and the shareholders of the project company RoPower Nuclear did the same the next day.1 2 The plant would use six reactors designed by the US firm NuScale. The United States has lent money for the preparatory work, but Nuclearelectrica's own announcement says the financing for construction is still to be defined.1 6
What was decided
The decision moves the project towards its third stage, called pre-EPC (the engineering and contracting work that comes before a construction contract).1 Nuclearelectrica holds 50% of RoPower Nuclear; the other half belongs to Nova Power & Gas, part of the Romanian E-Infra group. The plant would have six units of 77 MW each, 462 MW in total, on the site of the former 600 MW Doicești coal plant.1 2
Nuclearelectrica says the pre-EPC stage is estimated at 15 months and should produce a firmer budget estimate, the selection of contractors and a contract structure. It aims for the plant to be operating "at the beginning of the next decade", subject to corporate approvals and the regulatory framework.1 The Romanian business magazine Revista Biz quotes RoPower's chief executive, Valentin-Ovidiu Nae:
Adoptarea Deciziei Finale de Investiție confirmă că proiectul este pregătit să intre într-o nouă etapă.
The adoption of the Final Investment Decision confirms that the project is ready to enter a new stage.2
One reactor first
The decision is not a commitment to build all six units at once. Nuclearelectrica's release says only that the approval rests on "additional conditions" and does not list them.1 Balkan Green Energy News, citing Romanian news outlets, reports that the key condition is a plan to build and test one 77 MW reactor first, with the other five going ahead only if that trial succeeds.3
Nuclear Engineering International, citing the Romanian outlet Profit.ro, says Romania would pay for the first of the six modules, most likely through a credit line from Nuclearelectrica, and that the company has not published two annexes listing conditions that could end the project early or block the last five reactors. It adds that continuation depends on investigating and mitigating possible gas leaks reported at the site.4
The American part
NuScale is the technology provider, under a 2020 intergovernmental agreement between Romania and the United States that was ratified in 2021. Nuclear Engineering International also records a US grant of 14 million dollars for a preliminary engineering study, announced after the site was chosen in 2022.4
The largest confirmed US commitment is a loan. The Romanian daily Adevărul reported on 1 October 2024 that the US Export-Import Bank (EXIM, the federal export-credit agency) had approved up to 99 million dollars for RoPower Nuclear, as part of an initial package of 275 million dollars that also involves the US International Development Finance Corporation (DFC) and private partners.6 Balkan Green Energy News gave the loan as 98 million dollars for pre-project services, and reported that EXIM and DFC had expressed interest in providing up to 3 billion and 1 billion dollars respectively.7 Those larger sums are expressions of interest, not approved loans.
For construction itself, none of the pages read for this article names a lender. In Nuclearelectrica's release, Energy Minister Bogdan Ivan says that over the following six months the project would define its financing mechanisms and advance talks with potential investors.1
Costs are not settled
The estimates differ by source, and in one case by currency. Romania's Ministry of Energy valued the project at 4.9 billion dollars in 2024, according to Balkan Green Energy News.7 Nuclear Engineering International, citing Profit.ro's account of ministry and company documents, gives about 4.9 billion dollars for the whole project, plus or minus 20 to 30%, and about 600 million dollars for the pre-EPC stage.4 Balkan Green Energy News's February 2026 report gives the same number in euros, 4.9 billion.3 The Czech energy site oenergetice.cz puts construction at between 6 and 7 billion dollars; the open part of that page gives no basis for the figure.5
On timing, oenergetice.cz expects commercial operation in 2033, and Balkan Green Energy News says earlier projections had the first unit online in mid-2033.3 5
What to watch
The six-month period the minister described ran out around mid-August 2026.1 The pages read for this article report no outcome, so whether a financing structure has been set is unconfirmed. The Romanian financial daily Ziarul Financiar reported on 16 May 2026 that Nuclearelectrica had told investors the project had entered the phase before contracting a builder, without giving a date for the start of construction or saying how many of the February conditions had been met.8 If the 15 months are counted from May 2026, the pre-EPC stage would end around August 2027; the company has not published that date.1 8