An EACOP invitation for pipeline-inspection services in Uganda closed on 16 November 2026, setting conditions for suppliers seeking work on the future crude-export route. The amended notice envisages a combined contract with registered entities or local partners in Uganda and Tanzania, with each partner providing services across the relevant section.1
Applicants needed active registration on Uganda's petroleum supplier database, tax registration and clearance, and a statement of compliance with national-content regulations. They also had to demonstrate experience inspecting heated or waxy-crude pipelines. The planned work includes detecting deformation, metal loss and cracks, with inspections of two segments scheduled for the 2027 operational year.1
Supplier selection precedes operational evidence
The invitation is a procurement step, not a contract award or proof that crude is flowing. Its notice says only pre-qualified applicants will receive an invitation to bid after signing a confidentiality agreement.1
The broader timetable has continued to move. In a report published on 16 November, The EastAfrican quoted EACOP deputy managing director John Bosco Habumugisha putting project completion at 96% and targeting the end of February 2027 for completion. That is a management target, rather than a completed commissioning milestone.2
The report said the Petroleum Authority of Uganda attributed delays partly to disrupted deliveries of specialised equipment following the Middle East conflict. It distinguished the physical pipeline from pumping, pressure-control, storage and marine-export facilities that must also be tested. Its account therefore does not establish that completing the pipe alone immediately releases an export cargo.2
Construction progress leaves testing work
TotalEnergies' French progress update, reporting the position at 30 September 2026, describes EACOP moving towards the next stage.3
les activités de test et d’énergisation
testing and energisation activities.3
The company said station foundations and structural and piping work were complete, while attention was turning to electrical and instrumentation cabling and pre-commissioning. At Tanga, it reported storage tanks ready for commissioning tests and loading-arm installation continuing. Those are different stages of readiness along the same route, not an announcement that commercial exports have begun.3
The company's account also explains the operating constraint: Tilenga's crude needs to remain above 50°C during transport. Insulation and heat-management systems are therefore part of the export infrastructure, rather than optional additions after construction.3
Uganda's own official explanation makes the connection between projects explicit. An Energy Ministry account published through the Uganda Media Centre in August said Tilenga, Kingfisher and EACOP had to be ready together before first oil could be announced. It described commissioning as testing installed components to establish that they function.4
The same account placed the planned domestic refinery at an earlier design stage, following first oil. Refinery plans should consequently be distinguished from the facilities needed to deliver the initial crude through Tanzania. For the export route, the next substantive evidence is completed testing across the linked installations and an operational start announcement.4