US weapons that Washington has approved for Taiwan but not yet delivered are worth about US$29.72 billion (about NT$936.1 billion), according to the Taiwan Arms Backlog Tracker run by the Taiwan Security Monitor at George Mason University, as cited by the United Daily News on 1 October 2026. Taiwan's defence ministry told the legislature in October that three of its 24 active US purchases are officially delayed.1 2
The tracker's figure has grown. In December 2025 Central News Agency, citing Nikkei Asia's reading of the same George Mason data, put the backlog at about US$21.5 billion as of October 2025. On 17 December 2025 the State Department notified Congress of an US$11.1 billion package, the largest to that date.3
What Taipei says is late
The defence ministry's written report to the Legislative Yuan, carried by Central News Agency on 24 October 2026, names three delayed cases:2
- F-16 Block 70. 66 jets in a NT$247.2 billion programme. All were to be flown to Taiwan in 2026; the first two reached Taitung air base on 2 October 2026, and the ministry cites a production line move and restart and supply-chain disruption.2
- AGM-154C glide bombs. Due in 2023, now expected in 2028, because the US is building the newest configuration and had to restart its line.2
- Mk-48 heavy torpedoes. 24 combat and four exercise torpedoes, NT$5.46 billion. Due in 2026, now 2028, after supply-chain disruption and a line restart.2
By mid-November five F-16 Block 70 jets had arrived, the Taipei Times reported. Defence Minister Wellington Koo (顧立雄) confirmed in September that full delivery would not be completed this year and that the contract has no penalty clause, but said there were compensation measures; China Times, cited by Mirror Daily, reported these as more technical services, spare parts and longer warranties. Koo said:4 5
美方已經釋出善意
The US side has already shown goodwill.5
Items moving, some years behind
The same ministry report lists Abrams M1A2T tanks and Switchblade 300 drones as fully delivered this year, and Stinger missiles, the Harpoon coastal defence system, MS-110 reconnaissance pods and MQ-9B drones as arriving during 2026. The Patriot upgrade, with 102 PAC-3 MSE missiles, is due to finish in 2027.2
- Stinger. The first purchase agreement was signed in 2017. Koo said on 3 November 2026 that the first 500 missiles would arrive from the fourth quarter of this year; the schedule for a second batch of 2,121 is still under discussion.6
- HIMARS. Eleven launchers arrived in 2024. Eighteen more, originally due in 2027, are expected by the end of 2026 after the US changed its production priorities. A further 82 from the December 2025 package are expected from 2030, the Liberty Times reported.7
- Harpoon coastal defence. Approved in 2020, deliveries began in 2025 with completion expected by 2028, according to the December 2025 report.3
Causes each side gives
Taiwan's ministry blames line restarts and supply chains.2 The Liberty Times, citing an unnamed senior military source, reported that US output of PAC-3 MSE interceptors is about 600 to 650 a year, that US forces and NATO and Gulf buyers stand ahead of Taiwan, and that any extra PAC-3 MSE missiles from a new sale would arrive no earlier than late 2031.8
Washington has also paused deliveries for its own needs. Acting Navy Secretary Hung Cao told a Senate appropriations panel in May 2026 that sales were on hold during the US operation against Iran:9
"Right now we're doing a pause in order to make sure we have the munitions we need for Epic Fury."9
Taiwanese scholars disagree on the main cause. Su Tzu-yun (蘇紫雲) of the Institute for National Defense and Security Research calls it chiefly technical, pointing to the F-16 line's move from Fort Worth to Greenville, while Liao Tien-wei (廖天威) of Chinese Culture University says the spread of delays across many weapon types points to politics, including US-China summit diplomacy.1
Notices and lawmakers
US arms notices reach the Federal Register long after Congress hears of them. Notices published on 15 December 2025 cover three NASAMS air defence units worth US$1.16 billion and radars worth US$828 million, both reported to Congress on 25 October 2024. A US$265 million datalink notice published on 12 January 2026 went to Congress on 20 December 2024.10 11 12
A separate package of about US$14 billion, informally cleared by senior lawmakers in January 2026, has not been formally notified, Taiwan News reported. Bonnie Glaser and Noah Munk of the German Marshall Fund urged the White House to resume regular notifications and to send part of the package now.13 The Senate Appropriations Committee's draft defence bill for fiscal 2027, released on 16 November 2026, says the US$14 billion sale has been delayed without cause and that US$1 billion appropriated for Taiwan security cooperation in fiscal 2026 remains unspent; it would require the defence secretary to explain the delay within 30 days of enactment.14
The next markers are the end of 2026, when Taipei expects the remaining HIMARS of the first two batches and the first Stingers, and the full Senate and House votes on the fiscal 2027 bills.6 7 14